What is the effect of sloping a trench compared to simply shoring it?

Prepare for the Rhode Island Heavy Equipment Operator Test. Use flashcards and multiple choice questions, with hints and explanations for each question. Gear up for your exam!

When comparing the effects of sloping a trench versus simply shoring it, sloping generally requires the removal of more material. This is because creating a safe slope involves cutting back the walls of the trench at an angle to prevent collapse, thereby widening the trench at its top.

Shoring, on the other hand, usually involves supporting the vertical walls to prevent them from collapsing without altering the trench's width significantly. As a result, a shored trench can maintain its vertical walls, allowing for more efficient use of space and material removal. However, when a trench is sloped, the additional material that needs to be excavated is not only from the trench depth but also includes the area at the top, which ultimately leads to increased material removal.

Being aware of these differences is crucial for heavy equipment operators as it impacts safety, efficiency, and environmental considerations during excavation work.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy